2021 Stormwater Pond Maintenance Project

Overview

The City is implementing its annual stormwater pond maintenance project (see project map below). These project locations were chosen based on the comprehensive survey and subsequent prioritization of the City’s entire network of stormwater ponds completed in fall of 2020. This is the first project in what is anticipated to be a robust annual stormwater pond maintenance program. This work will be paid for utilizing the Surface Water Management Fees collected with utility bills and new developments, with no additional cost to property owners.

The general scope of work includes removing obstructions to access the ponds, cleaning out accumulated sediment, stabilizing eroded areas, repairing storm pipes and structures, and restoring the disturbed areas.  All work will be performed within city owned easements.  The 2021 projects are currently moving into construction, with final restoration occurring in spring 2022.

Access to the ponds will be different at each location and the City will work with adjacent property owners ahead of and during construction to communicate the scope of work. It is likely that some trees and other vegetation may need to be removed in order to access each pond. 

If you have any questions about this program or the particular work at these locations, please contact the City’s Construction Manager, Matt Petite at mpetite@ci.chanhassen.mn.us or at 952-227-1168.


2021 Stormwater Pond Maintenance Map

  1. Matt Petite

    Engineering Technician/ Construction Manager
    Phone: (952) 227-1166 Cell: (612) 358-7085

  2. Joe Seidl

    Water Resources Engineer
    Phone: (952) 227-1168

NotifyMeKaren_thumb.png Opens in new window
Click on the Notify Me button
to sign up with your email
and/or cell phone number to receive project updates. The information provided will be general in nature, such as proposed project schedule
and upcoming construction activities. 

Project Updates

Come back to this page for project updates or click on the “Notify Me” icon to have updates automatically sent to you by email and/or text message.

January 21, 2022

Work is ongoing at Site 4 (Buckingwood Ct) and the contractor will be working on Saturday, January 22nd from 9am to 5pm. The project schedule has been updated to reflect the proposed dates for each site. See the Project Schedule box below.

January 7, 2022

Work will begin next week for the Stormwater Pond Maintenance Project and is scheduled to start at Site 4 on Monday, January 10th.  The work will consist of removing sediment from the ponds and various storm sewer improvements. 

As with any construction project, you should expect to see workers and equipment near and around the pond.  Keep in mind that the allowable hours of activity, under the City’s ordinance, is 7am-6pm on weekdays.

Project Schedule
Bid OpeningOctober 27, 2021
Council ApprovalNovember 8, 2021
Construction @ Site 4 (Buckingwood Ct)January 10 - February 4, 2022
Construction @ Site 1 (Bittern Ct)January 25 - February 8, 2022
Construction @ Site 2 (Frontier Trl)January 7 - February 11, 2022
Construction @ Site 3 (Carver Beach Rd)February 11 - February 25, 2022
Construction @ Site 5 (Mulberry Cir)February 21 - March 4, 2022
*Construction dates are tentative-Changes to the schedule will be posted