Project Updates


September 17, 2020

Communication services have been repaired and things should be back to normal.  Thank you for your patience.

Next week, asphalt and concrete removals will take place in southern end of section 2 along with work being done on the storm sewer and sanitary sewer. Concrete placement in section 1 will occur midweek. The last two pipe bursts in section 2 will be completed and then crews will proceed with water testing on that section.  Preparations for section 3 valve installations will take place and any affected properties will be notified directly. Please use caution when driving through the project. 

September 17, 2020

An unmarked communication service line was impacted by construction activities as part of the Minnewashta Pkwy project a short time ago and there may be service outages as a result.  The utility company has been notified and they are dispatching a repair crew.  Service should resume within the next several hours. We are sorry for any inconvenience this may cause.


September 11, 2020

Next week, asphalt and concrete removals will continue to take place in section 1, along with work being done on the storm sewer and sanitary sewer. The last two water services will be completed and the temporary water will be disassembled in section 1 as well. Crews will complete work on the water main in section 2 and proceed with testing on that section. Preparations for sanitary sewer lining will take place and crews will be jetting and televising from 77th Street to King’s Road. School bus traffic through the project site will be accommodated.

September 10, 2020

Next week, asphalt and concrete removals will take place in section 1 along with work being done on the storm sewer and sanitary sewer.  The last two water services will be completed and the temporary water will be disassembled.  Crews will complete work on the water main in section 2 and proceed with water testing on that section.  Preparations for sanitary sewer lining will take place and crews will be jetting and televising from 77th Street to King’s Road.

September 3, 2020

Next week, the remaining water services will get completed and storm sewer, as well as sanitary sewer repairs will begin in Section 1.  In Section 2, pipe bursting continues along with tie-ins and hydrant installation.  
Crews will be off for Labor Day, so no work will be going on during the holiday weekend.  Crews will be back to work Tuesday morning.  Have an enjoyable and safe holiday weekend!

August 27, 2020

Work on the water main continues as temporary water is still in place from Lakeridge Road to Red Cedar Point Road.  Pipe bursting in section 2 continues to move north.  The full closure of the road will involve the entire intersection at Lakeridge Road through roughly 150 feet north of the intersection, as an open trench will need to be dug to complete some of the work.  This is expected to begin the middle of next week and no vehicle or pedestrian traffic will be able to move through this area while the open trench remains.  Late next week, an additional crew will be added to work on catch basins and manholes in section 1.  As always, please do not attempt to move or go around barriers and use caution when traveling around the work zone.

The project manager will be in continual contact with the school bus company, providing them with the latest information, as students go back to school.  Please look to the school bus company for more information on how they will be accommodating riders.

August 17, 2020

A communication utility was damaged late last week and caused some outages. CenturyLink personnel is onsite and finishing up the repairs and service has been restored. We apologize for any inconvenience this caused. 

August 13, 2020

Water was restored to properties in the Red Cedar Point Road and Maple Shores Drive area, and work on setting up temporary water continues in section two.  For the remainder of this week and next week, the contractor will be installing services in section one and proceeding to start pipe bursting in section two.

We are ready to shift the road closure to the north.  By the end of the day, the hard closure should be at the intersection of Minnewashta Parkway and Lakeridge Road.  

Everyone on Hawthorne Circle and south should now be entering the neighborhood via Hwy 5 and everyone North of Lakeridge Road should be accessing the area via Hwy 7.  Access to Lakeridge Road will come from the south, off of Minnewashta Parkway at Tristan Drive, to Ridge Hill Road and then to Lakeridge Road.  Click here to see a map of this area.

Please do not attempt to move or go around barriers and use caution when traveling around the work zone.

August 11, 2020

An unforeseen issue with a connection at Red Cedar Point Road, caused the water to be shut down.  The shut down is affecting properties on Red Cedar Point Road and Maple Shores Drive.  Water will be restored as soon as possible.  Crews will be in the neighborhood, knocking on doors to notify residents.  We apologize for any inconvenience this has caused.

August 6, 2020

This week, the contractor is working on pressure testing and bacteria testing of the new watermain.

Next week, crews will be cutting in the new valve at Red Cedar Point, installing water services in section 1, and working on setting up homes in section 2 with temporary water.  Impacted homeowners will be notified ahead of time.

The week of August 17, the contractor will be pipe bursting in section 2.  This activity will cause a shift in the full road closure to the north.  We will keep you posted on the traffic control change as it gets closer.  For now please remember, residents in the Trolls Glen Neighborhood should continue to utilize Highway 5 to access their homes and all others North of West 77th Street should be utilizing Highway 7 to access their properties.  Please use caution when traveling or walking around the work zone.

July 30, 2020

Week of July 27: The contractor is finishing the set-up and testing of the temp water for section two. They will have made all the connections to the new main in section one and will proceed with flushing this weekend.

Week of Aug. 3:  The contractor will test the new main in section one and start installing services. They will notify and start hooking up residents in section two, to temp water later in the week, after the last valve is cut in at Red Cedar Point Rd. Those activities will be followed up with pipe bursting prep and bursting in section two.

Residents in the Trolls Glen Neighborhood should continue to utilize Highway 5 to access their homes and all others North of West 77th Street should be utilizing Highway 7 to access their properties.  Please use caution when traveling or walking around the work zone.

July 22, 2020

Week of July 20: Contractors continue to cut in new valves and make connections to the new main. They continue to work on setting up temporary water between Lakeridge Drive and Red Cedar Point, (Section 2).
Week of July 27:  Contractors will be cutting in the last few valves for Section 2 the first part of the week.  Temporary water for Section 2 and new main for Section 1 will be tested.  Once they have passed the tests, homes in Section 1 will be hooked up to the new system.  This is expected to happen around the end of the week.  Pipe bursting activity continues to move north towards Minnewashta Court.  Residents affected will be notified in advance.

Residents in the Trolls Glen Neighborhood should utilize Highway 5 to access their homes and all others North of West 77th Street should be utilizing Highway 7 to access their properties.  Please use caution when traveling or walking around the work zone.

July 17, 2020

Pipe bursting continues this week and next from West 77th Street to Lakeridge Drive, along with connecting the new watermain into the existing watermain. The installing of new gate valves from Lakeridge Drive to Red Cedar Point was pushed back from the week of July 13th to the week of July 20th.  Contractors will then be testing the new main and assembling temporary water for the next phase.

The week of July 27, contractors will be installing new services from West 77th Street to Lakeridge Drive.  The pipebursting activity will move North from Lakeridge Drive towards Minnewashta Court. 

July 10, 2020

Pipe bursting continues this week and next. Next week the contractor will also be installing new gate valves from Lakeridge Drive to Red Cedar Point and any residence affected by this work will be directly notified in advance of the work taking place and prior to any interruption of service.

Residents in the Trolls Glen Neighborhood should utilize Highway 5 to access their homes and all others North of
West 77th Street should be utilizing Highway 7 to access their properties.  Please use caution when traveling or walking around the work zone.

June 29, 2020

The contractor will not be working today due to the rain, but will continue pipe bursting through the remainder of this week. They will not be working Friday July 3rd or Saturday July 4th. For public safety all traffic control devices and barricades will remain in place and should not be tampered with or moved.

Residents in the Trolls Glen Neighborhood should utilize Highway 5 to access their homes and all others North of West 77th Street should be utilizing Highway 7 to access their properties.  Please use caution when traveling or walking around the work zone.

June 19, 2020

The contractor is still prepping for pipe bursting and testing temporary watermain to assure compliance with City standards for potable water. They anticipate hooking up homes to temporary water next Monday morning (6/22) and all affected residents will be notified directly prior to. Pipe bursting to begin midway through next week and will take approximately 2-3 weeks to complete dependent upon weather and site conditions.

Residents in the Trolls Glen Neighborhood should utilize Highway 5 to access their homes and all others North of West 77th Street should be utilizing Highway 7 to access their properties.  Please use caution when traveling or walking around the work zone.

June 17, 2020

A private unmarked gas service was impacted by construction activities as part of the Minnewashta Pkwy project a short time ago and there may be service outages as a result.  Centerpoint Energy and the Fire Department have been notified and they are dispatching a repair crew.  Service should resume within the next several hours. We are sorry for any inconvenience this may cause.  If you are directly impacted or for more information you may contact Centerpoint Energy at 612-372-4727.

June 9, 2020

In addition to the water shutdowns yesterday and today, the Contractor is planning additional shutdowns on Thursday and Friday of this week.  They are planning their work around the weather forecast.  The properties affected by each shutdown will be notified approximately 48 hours in advance of the shutdown.  A flyer will be left at each residence with the pertinent information.

June 5, 2020

The Contractor has been working on setting up temporary water and getting prepared for starting on the replacement of the water distribution system.  On Monday or Tuesday, June 8th or 9th, they plan to begin installing new gate valves.  This operation will require temporary water shut-offs during the day for an estimated total of 3 days.  Home owners who will be affected by a planned temporary water shut-off will be notified by the contractor 48 hours in advance of the shut-down.  The Contractor will leave a flyer at your home for the notifications.  We do everything we can ahead of time to plan to keep the least amount of properties as possible impacted by a water shut-off.  Please be aware that at times certain control valves do not function properly that are needed to shut-off the water per the plan.  This is one reason they are being replaced.  In the case of a planned shut-off where a valve doesn’t function – the Contractor will need to expand the area of the shutdown and additional properties will be affected.  In this case, an emergency shutdown notice will be delivered to the additional properties notifying them of the shutdown.

Throughout the week the temporary water lines will be tested to assure compliance with City standards for potable water.  Further prep work for the new water lines will also take place throughout the rest of the week.  Some additional clearing and grubbing may also occur.  The majority of the tree clearing for phase 1 has been completed.

The following week, residents will be switched over to the temporary water lines and again will be notified 48 hours in advance of the switchover.  Once everyone has been transitioned to temporary water, the contractors will begin the process of pipe bursting, a mostly trenchless way to install the new pipes.  Please be aware there will be excavation pits in the street where the contractor will be performing pipe bursting operations.

Please go slow and use caution if you need to travel through the construction zone.  Any resident who lives north of Lakebridge Rd is asked to use TH 7 to access their property and stay out of the zone where construction is occurring for safety purposes.

May 21, 2020

Beginning Tuesday, May 26th, Minnewashta Parkway will be closed to through traffic, for construction in Phase 1, Highway 5 to Kings Road. Contractors will be clearing and grubbing, installing erosion control, and setting up the staging area at Roundhouse Park. Please use caution in that area.

Phase 1 will be further broken down into 3 parts. Part A will be from Hwy 5 to Lakeridge Road, Part B will be from Lakeridge Road to Red Cedar Point Road and Part C will be from Red Cedar Point Road to Kings Road. Part A will be set up for temporary water next week. It is recommended that residents living North of Lakeridge Road access the area from Hwy 7.

May 18, 2020

The Road Closure scheduled for Monday, May 18th has been postponed until after the upcoming holiday. The closure is now scheduled to begin on Tuesday, May 26th. Some minor work is taking place in preparation for the road closure. Please continue to check back for updates on the contractors schedule and the progress of this project. If you would like to receive these updates via email and/or text message, click the Notify Me box near the bottom of this page to subscribe.

May 11, 2020

A pre-construction meeting with the contractor took place last week. Construction on Phase I will begin on Monday, May 18th with a Road Closure on the southern section of roadway.
Please continue to check back for updates on the contractors schedule and the progress of this project. If you would like to receive these updates via email and/or text message, click the Notify Me box near the bottom of this page to subscribe.

May 4, 2020

A pre-construction meeting with the contractor is scheduled for later this week. Please continue to check back for updates on the contractors schedule and the progress of this project. If you would like to receive these updates via email and/or text message, click the Notify Me box near the bottom of this page to subscribe.

April 14, 2020

The Assessment Hearing is scheduled for the April 27th 2020, City Council Meeting. Due to the City’s response to the COVID-19 pandemic, please click here for the latest information on how to participate in that meeting.

March 19, 2020

The March 24th Neighborhood Meeting has been Canceled due to the City’s response to the COVID-19 pandemic. Please check the Related Resources section above to see the information that was to be presented at that meeting.

March 13, 2020

A Neighborhood Meeting has been scheduled for Tuesday, March 24, 2020
from 4:30 - 6:00pm. The meeting will take place at the Chanhassen Recreation Center, 2310 Coulter Blvd. No formal presentation is planned. Please stop by at any time. This meeting will allow the public to view the planned improvements and get answers to any questions they may have about the project.