Overview

The adoption of a new franchise fee has allowed the City to invest substantially more in the maintenance and preservation of our local roads, which can be seen from the scope of the 2021 City Pavement Rehabilitation project. This project will incorporate multiple roadway treatments (mill & overlay, full depth reclamation, etc.) depending on the condition of the road for each area, along with minor spot repairs on existing utilities.

A total of seven (7) miles of roadway is proposed to be improved, so the project has been broken up into six areas; the Lake Lucy Road area (east of Powers Boulevard), Choctaw Circle area, Kurvers Point Road area, Marsh Drive area, Redwing Lane area, and the Trappers Pass area. The project is anticipated to begin in the summer of 2021, with work scheduled to be completed in the fall of 2021. Residents that utilize the streets within the project areas will be notified if access is limited.

This project was originally planned for 2020, however In light of recent state funding losses stemming from the COVID-19 pandemic and out of concern for the potential negative economic impact assessments might have on some Chanhassen residents, the City Council voted to postpone the planned road construction project and reassess at a later time.  It is now scheduled to take place during the 2021 construction season.

Click Here for a full map of the project areas.


Related Resources

Construction Newsletter

Assessment Practice
The City of Chanhassen's Assessment Practice is intended to provide direction to City Staff in preparation of assessment rolls for public improvements, to ensure fair and consistent treatment of all properties within the City of Chanhassen.

Pavement Management
Pavement Management Questions/Answers


Project Updates

October 20, 2021

Trapper Pass Phase 2: Tomorrow morning a crew will be on-site to mill joints and work on a small asphalt patch on Cascade Pass in preparation for wear course paving. Paving will occur on Near Mountain Blvd, Piedmont Ct, Castle Ridge, Shasta Cir E, Cascade Cir, Cascade Ct, Cascade Pass. Paving operations are planned to finish up tomorrow. The contractor will also adjust the manhole castings and gate valves along Timber Hill Rd tomorrow morning and if time allows they may also finish paving on that road. Irrigation and Invisible fence repairs, landscaping, restoration, and punch list work will be taking place over the next few weeks.  

Kurvers Point Road Area: Irrigation repairs are beginning this week and invisible fence repairs will take place afterwards. Placement of topsoil will continue for the remainder of this week and seeding is tentatively scheduled to being next week or the following week. Adjustments for manhole castings and gate valves in the street are tentatively scheduled for October 27th and 28th in preparation for the wear course paving which is tentatively scheduled for October 29th.

Marsh Drive Area: Adjustments to manhole castings and gate valves are scheduled to occur this Friday, October 22nd and Monday, October 25th. Prep work consisting of milling pavement joints in various areas in the area and two small asphalt patches will be removed and replaced in the street on Dakota Lane on Tuesday, October 26. Wear course paving is tentatively scheduled for October 27th and 28th.

Lake Lucy Road Area, Redwing Lane Area, Choctaw Circle Area, and Trappers Pass Phase 1: These areas have primarily been completed except for some minor work that is not weather dependent and essential to the operation of the streets.  There are also some other minor follow-up (punch list) type of items that staff continues to follow-up with the contractor on. Inlet protection has been taken out in some areas and will continue to be removed over the next few weeks.

 


Previously Posted Updates


Project Areas

This project is divided into six neighborhood areas. Trappers Pass is the largest area and will be divided into two construction phases.

Here are the Estimated Construction Dates for Each Area:

Lake Lucy Road areaMay 17 - July 15
Redwing Lane areaJune 11 - July 24
Choctaw Circle areaJune 22 - Aug 5
Trappers Pass-1 area (See Map)June 30 - Oct 7
Trappers Pass-2 area (See Map)July 26 - Oct 7
Marsh Drive areaAug 23 - Nov 5
Kurvers Point Road areaSept 20 - Nov 4

Substantial completion is expected by November 2021.  Stormwater pond clean-out work will occur in the Trapper's Pass area during the winter of 2021/2022.  Final restoration is planned during the spring of 2022. 

Project Schedule

Revised for 2021 Project Start
Accept Feasibility Report/Call Public HearingJanuary 11, 2021
Public HearingJanuary 25, 2021
Approve Plans & Specifications/Authorize BiddingFebruary 8, 2021
Bid OpeningMarch 12, 2021
Public Information Open HouseApril 14, 2021
Assessment Hearing/Award ContractApril 26, 2021
Start ConstructionMay 2021
Substantial CompletionNovember 2021
Project Notification Disclaimer
Due to the variability of construction, updates typically do not include specific details such as day-to-day scheduled activity. The City's inspector or contractor will notify occupants directly if they will be impacted by a utility service shut down (example: water shutoff), or work (such as excavation or new curb) that will impede access to the property for a period of hours or days.