- Home
- Your Government
- Departments
- Engineering / GIS
- Projects
- Street Projects
- 2022 City Pavement Rehabilitation Project
2022 City Pavement Rehabilitation Project
-
Matt Petite
Engineering Technician/ Construction ManagerPhone: (952) 227-1166 Cell: (612) 358-7085
-
George Bender
Assistant City EngineerPhone: (952) 227-1164
Overview
Approximately five (5) miles of roadway are proposed to be rehabilitated in three different neighborhoods. The areas proposed for improvements are shown in more detail on these maps.
• The Brinker area lies on the east side of CR 117 (Galpin Blvd) with approximately 1.0 mile of streets built-out around 1993.
• The Longacres area lies on the east side of Lake Minnewashta between TH 41 (Hazeltine Blvd) and CR 117 (Galpin Blvd), with approximately 2.2 miles of streets built-out between 1992 and 1997.
• The Stone Creek area lies northeast of the intersection of CSAH 19 (Galpin Blvd) and CSAH 18 (Lyman Blvd), with approximately 1.5 miles of streets built-out between 1992 and 1994.
Neighborhood Area | To Include |
Brinker area | Majestic Way, Windmill Drive, Walnut Curve, Brinker Street, Tulip Court, Crocus Court |
Longacres area | Hillsdale Court, Gunflint Court, Gunflint Trail from Longacres Drive to 150 feet north of Gunflint Court, Moccasin Trail, Southern Court, Bent Bow Trail, Hunter Drive, Fawn Hill Court, Fawn Hill Road from Longacres Drive to 225 feet south of Fawn Hill Court, Red Fox Circle, Lodgepole Point, and Northwood Court |
Stone Creek area | Stone Creek Drive from Galpin Blvd to 250 feet east of Boulder Rd, Stone Creek Road, Stone Creek Lane West, Stone Creek Lane East, Stone Creek Court, Boulder Road |
None of these areas have had major rehabilitations performed after their original construction (only maintenance activities such as crack seals, chip seals and pothole patching). All project areas need to be evaluated with anticipated improvements to include:
• full depth reclamation
• mill and overlay (full depth or partial)
• spot soil corrections or reconstruction
• spot curb and gutter replacement
• ADA improvements
• stormwater management spot repairs
• sanitary sewer spot repairs
• watermain spot repairs
Project Updates
May 13, 2022
Council approved the assessment and awarded the contract at the May 9th City Council meeting. GMH Asphalt, Co. is the prime contractor for the project. A pre-construction meeting was held with the contractor and the following tentative construction schedule was determined:
- Start Construction May 23, 2022
- Brinker Area Tentative Construction Dates May 23 – July 15, 2022
- Longacres Area Tentative Construction Dates June 13 – September 2, 2022
- Stone Creek Area Tentative Construction Dates July 18 – September 30, 2022
- Substantial Completion October, 2022
- Pond Cleaning Work January – March, 2023
- Final Completion June, 2023
Watch the mail for a construction newsletter that will provide more details about the construction project and keep an eye on the webpage for future updates. Generally, we will attempt to provide updates on a weekly basis.
Come back to this page for project updates, or use the Notify Me button, near the top of the page, to have the updates sent directly to you via email and/or text message.
Project Schedule
Dates are Tentative and Subject to Change | Check Back for Updates |
---|---|
Award Consultant Contract | October 25, 2021 |
Neighborhood Project Open House | December 15, 2021 |
Accept Feasibility Report/Call Public Hearing | January 24, 2022 |
Public Hearing | February 14, 2022 |
Approve Plans & Specifications/Authorize Bidding | March 14, 2022 |
Bid Opening | April 12, 2022 |
Neighborhood Open House | May 3, 2022 |
Assessment Hearing/Award Contract | May 9, 2022 |
Start Construction | May 23, 2022 |
Brinker Area Tentative Construction Dates | May 23 - July 15, 2022 |
Longacres Area Tentative Construction Dates | June 13 - September 2, 2022 |
Stone Creek Tentative Construction Dates | July 18 - September 30, 2022 |
Substantial Completion | October, 2022 |
Pond Cleaning Work | January - March, 2023 |
Final Completion | June, 2023 |
Related Resources
A Public Open House was held on December 15, 2021. Here is some information from the event.
Project Display
Assessment Information
Neighborhood Maps
In the ‘Neighborhood Maps’ link, you will notice the following items:
• On Figure 1: Stone Creek Area Improvements there is a ‘Proposed Street Connection’ between Stone Creek Ct and Timberwood Dr.
• On Figures 3 & 4: Longacres Area Improvements there are ‘Proposed Removal of Center Islands’.
Please note that neither of these options considered in the Feasibility Study for the project, will be pursued through the design and construction phases of this rehabilitation project.
Project Notification Disclaimer |
---|
Due to the variability of construction, updates typically do not include specific details such as day-to-day scheduled activity. The City's inspector or contractor will notify occupants directly if they will be impacted by a utility service shut down (example: water shutoff), or work (such as excavation or new curb) that will impede access to the property for a period of hours or days. |