Overview

The adoption of a new franchise fee has allowed the City to invest substantially more in the maintenance and preservation of our local roads, which can be seen from the scope of the 2021 City Pavement Rehabilitation project. This project will incorporate multiple roadway treatments (mill & overlay, full depth reclamation, etc.) depending on the condition of the road for each area, along with minor spot repairs on existing utilities.

A total of seven (7) miles of roadway is proposed to be improved, so the project has been broken up into six areas; the Lake Lucy Road area (east of Powers Boulevard), Choctaw Circle area, Kurvers Point Road area, Marsh Drive area, Redwing Lane area, and the Trappers Pass area. The project is anticipated to begin in the summer of 2021, with work scheduled to be completed in the fall of 2021. Residents that utilize the streets within the project areas will be notified if access is limited.

This project was originally planned for 2020, however In light of recent state funding losses stemming from the COVID-19 pandemic and out of concern for the potential negative economic impact assessments might have on some Chanhassen residents, the City Council voted to postpone the planned road construction project and reassess at a later time.  It is now scheduled to take place during the 2021 construction season.

Click Here for a full map of the project areas.


Related Resources

Construction Newsletter

Assessment Practice
The City of Chanhassen's Assessment Practice is intended to provide direction to City Staff in preparation of assessment rolls for public improvements, to ensure fair and consistent treatment of all properties within the City of Chanhassen.

Pavement Management
Pavement Management Questions/Answers


Project Updates

October 14, 2021

Kurvers Point Road Area:  Paving of the base course will begin this afternoon around 12:30pm, tentatively and continue into tomorrow.  We are working with the school bus company to minimize any impacts this may have on bus routes.  Parents meeting the bus, please keep vehicles out of the way of paving equipment. Contractors are tentatively scheduled to finish concrete work on Friday. Next week, contractors will be doing some patching and driveways, backfilling with top soil and seeding, and adjusting the manhole castings and gate valves in preparation for the wear course paving, which is tentatively scheduled for October 29th

Marsh Drive Area:  Contractors will be adjusting manhole castings and gate valves, along with other prep work next week.  Paving is tentatively scheduled for October 27 and 28th.

Trapper Pass Phase 1:  Irrigation & invisible fence repairs, landscaping & restoration, and punch list work will be taking place over the next few weeks.

Trapper Pass Phase 2:   Adjustments to manhole castings and gate valves in the street will be taking place today and into next week in preparation for paving the wear course which is tentatively scheduled for October 19th and 20th.  In the Timber Hill area, grading will be occurring on Monday, followed by base course paving on Wednesday of next week.  Wear course paving of Timber Hill is tentatively scheduled for October 29th.  Irrigation and Invisible fence repairs, landscaping, restoration, and punch list work will be taking place over the next few weeks.  

Lake Lucy Road Area, Redwing Lane Area and Choctaw Circle Area: Inlet protection has been taken out in some areas and will continue to be removed over the next few weeks. These three project areas will have work occurring intermittently over the next few weeks consisting of remaining punch list items.  


Previously Posted Updates


Project Areas

This project is divided into six neighborhood areas. Trappers Pass is the largest area and will be divided into two construction phases.

Here are the Estimated Construction Dates for Each Area:

Lake Lucy Road areaMay 17 - July 15
Redwing Lane areaJune 11 - July 24
Choctaw Circle areaJune 22 - Aug 5
Trappers Pass-1 area (See Map)June 30 - Oct 7
Trappers Pass-2 area (See Map)July 26 - Oct 7
Marsh Drive areaAug 23 - Nov 5
Kurvers Point Road areaSept 20 - Nov 4

Substantial completion is expected by November 2021.  Stormwater pond clean-out work will occur in the Trapper's Pass area during the winter of 2021/2022.  Final restoration is planned during the spring of 2022. 

Project Schedule

Revised for 2021 Project Start
Accept Feasibility Report/Call Public HearingJanuary 11, 2021
Public HearingJanuary 25, 2021
Approve Plans & Specifications/Authorize BiddingFebruary 8, 2021
Bid OpeningMarch 12, 2021
Public Information Open HouseApril 14, 2021
Assessment Hearing/Award ContractApril 26, 2021
Start ConstructionMay 2021
Substantial CompletionNovember 2021
Project Notification Disclaimer
Due to the variability of construction, updates typically do not include specific details such as day-to-day scheduled activity. The City's inspector or contractor will notify occupants directly if they will be impacted by a utility service shut down (example: water shutoff), or work (such as excavation or new curb) that will impede access to the property for a period of hours or days.