The City is proposing to rehabilitate approximately 2 miles of streets as identified by it's Pavement Management software, site investigations and reported utility problems. This year's project includes several streets located in the Lake Susan Hills area.
bidresults.png

Project Updates


July 20, 2017

- The first layer of asphalt paving in Phase 1 is complete and will be followed up with a second layer after Phase 2 is paved. This week in Phase 2, crews have been reclaiming (grinding up) the old pavement. Storm sewer and water main work will be taking place this week and next week as well as curb removals and replacements.


July 5, 2017

- Bituminous base course paving to begin as early as Friday, July 7 followed by draintile installation in Phase 1. Curb removals, pavement reclaiming and utility work to begin the week of July 17 in Phase 2.

Anticipated Project Schedule

Project Phase
Date
Approve Plans & Specifications
January 23, 2017
Bid Opening February 15, 2017
Assessment Hearing; Award of Contract March 27, 2017
Construction Start June 12, 2017
Substantial Completion August, 2017
NotifyMeKaren_thumb.png

NEW!

 Click on the Notify Me button to sign up with your email and/or cell phone number to receive project updates. The information provided will be general in nature, such as proposed project schedule and upcoming construction activities. Due to the variability of construction, the updates typically do not include specific details such as day-to-day scheduled activity. The city's inspector will notify occupants directly if they will be impacted y a utility service shut down (example: water shutoff), or work (such as excavation or new curb) that will impede access to the property for a period of hours or days.