2016 Street Improvement Project - Minnewashta Manor Area

Overview


This project includes the reconstruction of Minnewashta Manor neighborhood in the summer of 2017. The streets will be reconstructed to the existing width and concrete curb and gutter is proposed to be installed. The water main under the street and the water services from the water main to the property line will be replaced. Some sanitary sewer repairs will be completed within the reconstruction area. Stormwater management improvements will also be made.
bidresults.png

Bids were received and opened on Tuesday, December 6, 2016. Acceptance of bids and award of contract is scheduled for Monday, January 23, 2017 at which time the Bid Alternate will be approved.
 

Project Updates

June 19, 2018

Phases I & IIA
Due to recent rains, the sod and landscape schedule has been delayed and will continue as soon as things dry out.

Washta Bay Road (Phase IIB)
Storm sewer work will continue and removal of temporary water will take place through this week followed by road construction beginning next week.


May 31, 2018

Phases I & IIA

Sod and landscaping will be installed over the next two weeks.

Washta Bay Road (Phase IIB)
T
his week and next week work will continue on water main and services. Storm sewer work will take place the week of June 11.

Project completion is planned for July, 2018.

Please Note: All schedules are weather permitting and may fluctuate in either direction of the anticipated dates.

NotifyMeKaren_thumb.png
Click on the Notify Me button to sign up with your email and/or cell phone number to receive project updates. The information provided will be general in nature, such as proposed project schedule and upcoming construction activities. Contact Jean at 952-227-1162 or by email for assistance.
Project Notifications Disclaimer
Due to the variability of construction, updates typically do not include specific details such as day-to-day scheduled activity. The City's inspector or contractor will notify occupants directly if they will be impacted by a utility service shut down (example: water shutoff), or work (such as excavation or new curb) that will impede access to the property for a period of hours or days.